Article Index
Twitter Posts
Friday
Sep232011

New Alcoholic Beverages Control Commission Member Named

Kathleen McNally to be Associate Commissioner of Massachusetts ABCC


Kathleen McNally was named this week to the three-member state Alcoholic Beverages Control Commission, which oversees liquor licensing activity in Massachusetts. She joins ABCC Chair Kim Gainsboro and Associate Commissioner Susan Corcoran. McNally worked as executive secretary and general counsel for the Licensing Board for the City of Boston from 1997 to 2002. Our brief canvas of professionals who have worked with McNally in the past revealed praise for her expertise, experience and calm demeanor.

September 23, 2011

 

Thursday
Sep152011

Damon Seligson named Super Lawyer

DSU partner Damon Seligson has been selected as a 2011 Massachusetts Super Lawyer for litigation by Super Lawyers magazine.  This is the 7th time Mr. Seligson has been selected by Super Lawyers magazine.

Thursday
Sep082011

Waiver of Subrogation - Good News for General Contractors

A recent Massachusetts Appeals Court case held that a waiver of subrogation clause was enforceable by the general contractor even though the general contractor failed to obtain a waiver of subrogation from a subcontractor as required by the general contract.  In North Am. Specialty Ins. Co. v. Payton Constr. Corp., Appeals Court No. 09-P-1391 (September 8, 2011), the all risk insurer sued a general contractor and two subcontractors as subrogee to the project owner after the insurer paid a claim for fire damage.  At issue was the American Institute of Architects A201 General Conditions, which contains the waiver of subrogation language.  That provision waives either party's rights against the other for claims covered by property insurance.  Therefore, when a property insurer pays a claim, even though it subrogates to the rights of that particular party (the owner in this case), the parties had previously waived those rights against one another and the insurer has no recourse.

The waiver of subrogation provision also required the general contractor to include similar provisions in its subcontracts with all of its subcontractors.  In North Am., the general contractor did not procure a waiver of subrogation with one of the subcontractors that was alleged to have caused (at least in part) the fire.  The insurer argued that the general contractor's failure to obtain a waiver of subrogation from the subcontractor was (1) a material breach of the general contract; and (2) as such, the entire waiver of subrogation provision was void and unenforceable.

The Superior Court and the Appeals Court disagreed.  The Appeals Court succintly held, "that the failure of a general contractor to obtain a waiver from a subcontractor under the AIA contract, in circumstances such as presented here, does not invalidate the subrogation waiver, nor does it render it unenforceable.  In short, the insurer, North American, is bound by the subrogation waiver set forth in the AIA contract at issue."

The waiver of subrogation clause is one of the most important clauses in a construction contract because it defines and limits risk.  This case is significant because (1) it enforced the waiver of subrogation clause; and (2) it enforced the clause even though there was a technical violation of the clause by the general contractor.  It is in the best interests of all parties to a construction project to have appropriately drafted waiver of subrogation clauses in all contracts.  However, in the event aproject participant does not consent to such a clause, this case makes it clear that a party that has a waiver of subrogation clause in its contract can utilize it, and it will be enforced.

Tuesday
Aug302011

Mechanic's Lien Law "Cram Down" Provision Enforced Again

On August 29, 2011, the Massachusetts Appeals Court issued a decision enforcing the "cram down" provision of the Mechanic's Lien Law, M.G.L. c. 254, section 4.  The case is Maverick Constr. Mgmt. Svcs., Inc. v. Fidelity & Deposit of Maryland, Inc., No. 10-P-998.  The "cram down" provision states that a subcontractor's lien is limited to the "amount due or to become due" the general contractor from the owner as the time the subcontractor's Notice of Contract is recorded.

The leading case on this issue is BloomSouth Flooring Corp. v. Boys' & Girls' Club of Taunton, Inc., 440 Mass. 618 (2003), issued by the Supreme Judicial Court.  In BloomSouth, the general contractor abandoned the project, and the subcontractors recorded their liens after the abandonment.  The SJC ruled that, once the general contractor abandoned the project, there was nothing due or to become due the general contractor and, as a result, the subcontractors' liens were valued at zero because they were recorded after the abandonment.

Maverick presented different facts.  In this case, the general contractor did not abandon the project.  Rather, the owner alleged that the general contractor's work was significantly deficient and withheld final payment.  The owner never formally terminated the general contractor, but did engage others to correct the deficient work.  The subcontractor recorded its Notice of Contract after the issues of defective work were raised by the owner with the general contractor.  The owner then recorded and served a lien bond to remove the lien from record

The dispute took two different paths.  Maverick sued the lien bond surety on its mechanic's lien.  The owner initiated arbitration against the general contractor.  The arbitration panel determined that the general contractor breached the contract and awarded damages to the owner.  The owner confirmed the arbitration award in court.  After that, the lien bond surety moved for summary judgment in Maverick's action to enforce the mechanic's lien, arguing that, pursuant to the Lien Law and the arbitration award, there was nothing due or to become due Maverick as of the date its Notice of Contract was recorded.  The Superior Court agreed and allowed the surety's motion.

On appeal, the Appeals Court affirmed the Superior Court's decision.  There are a few key issues in this decision.  First, the arbitration award was deemed to be final and conclusive as to the merits of the underlying matter between the owner and the general contractor.  Second, the fact that the general contractor did not abandon the project or the fact that the owner did not formally terminate the general contractor did not affect the analysis.  Third, even though the arbitration award did not specify the date of breach, the Court determined that the breach occurred prior to Maverick's recording of the Notice of Contract.  Since the general contractor breached the contract prior to Maverick's recording of the Notice of Contract, the Appeals Court affirmed the Superior Court's decision that there was no money due or to become due the general contractor at the time the Notice of Contract was recorded.

There are also practical considerations highlighted by this decision.  First, it was important that the arbitration concluded  before Maverick's mechanic's lien enforcement action concluded.  Depending upon whether you are an owner, general contractor, or subcontractor, the choice of forum (court or arbiration) can greatly impact the case.  Second, parties should consider joining in litigations or arbitrations (to the extent possible) so that all issues are resolved in one proceeding.  The viability of Maverick's mechanic's lien claim was unquestionably impacted by a private arbitration to which it was not a party.  

Thursday
Aug252011

Massachusetts Bid Protest Decisions Now On-Line

The Massachusetts Attorney General's Office is now publishing bid protest decisions on-line.  Here is the link -- http://www.bpd.ago.state.ma.us/