Article Index
Twitter Posts
« DSU Congratulates Its Clients On Making The BBJ's List Of The Top 25 Largest General Contractors In Massachusetts | Main | Massachusetts Mechanic's Lien Law "Cram Down" Provision Enforced - With A Twist »
Tuesday
Dec182012

Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201

A recent case issued by the Court of Appeals of Tennessee should give comfort to general contractors and pause to owners.  In RCR Building Corp. v. Pinnacle Hospitality Partners, 2012 WL 5830587 (Tenn. Ct. App. November 15, 2012), the Court held that the owner waived its claim against the general contractor for liquidated damages because it did not submit the claim in accordance with the procedures set forth in the contract.  The parties executed the AIA A111 Contract Agreement, which incorporated the AIA A201 General Conditions.  The owner asserted liquidated damages against the general contractor for delays.  The general contractor argued in a Motion for Partial Summary Judgment that the owner had failed to submit its claim for liquidated damages in accordance with the procedures set forth in the contract and, therefore, waived the claim.  The trial court rejected the general contractor’s argument.

On appeal, the Court of Appeals held that:  (1) pursuant to paragraph 4.3 of the A201, the owner’s claim for liquidated damages was, in fact, a claim as defined therein; and (2) the trial court should have allowed the general contractor’s motion because the owner failed to submit the claim in accordance with the contract.  The Court of Appeals rejected several arguments of the owner, including that a claim for liquidated damages is not a claim as defined by the A201 and that an owner’s claim for liquidated damages was self-executing.  In essence, the Court of Appeals held that the dispute resolution procedures in the contract were applicable to both contracting parties.

This can be a particularly useful case for general contractors in two distinct scenarios.  First, the obvious use is to defeat, potentially, an owner’s claim for liquidated damages for failure to comply with the contract’s notice provisions.  This case can also be used to defend an owner’s assertion of virtually any backcharge if the owner failed to comply with the notice provision.  Second, and less obvious, this case can help the contractor in negotiating the terms of its contracts with owners.  Often, owners will try to modify the A201 notice provisions and other provisions addressing claims by expressly limiting the applicability of those provisions to the general contractor’s claims only.  With this case, general contractors can now point to an appellate court decision that supports the clear and unambiguous language of the A201 in negotiating the terms of the claims provisions of the contract.

Please contact Jack DiNicola for additional information.

References (276)

References allow you to track sources for this article, as well as articles that were written in response to this article.
  • Response
    Response: news article
    I like this web blog very much, Its a rattling nice post to read and receive info . "Things do not change we change." by Henry David Thoreau.
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Ken Anderson ubs
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Ken Anderson ubs
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Ken Anderson ubs
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: dating sites
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: dumpsters
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: D D Photographics
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: asesoris hp
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Going On this page
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: More methods
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: check this out
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Arthur Falcone
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Arthur Falcone
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: best Maryland SEO
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: best SEO expert
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: justin peatling
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Createurs de Luxe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Createurs de Luxe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Createurs de Luxe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Red Payments
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Red Payments
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Red Payments
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Red Payments
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Red Payments
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Red Payments
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Red Payments
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Red Payments
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Brian Poe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Brian Poe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Brian Poe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Brian Poe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Brian Poe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: UK Models
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Brian Poe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: www.amazon.com
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: www.amazon.com
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Brian Poe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Brian Poe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Eric Gonchar
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Kion Kashefi
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Eric Gonchar
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Createurs de Luxe
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Kion Kashefi
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Boise SEO Review
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: wrench
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: headlamp
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Eric Gonchar
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Kion Kashefi
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: this site
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: wordpress
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: garcinia diet
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: GoPro Pole
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: NutriBullet
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: GoPro Mounts
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: GoPro Stick
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Bewu.pl
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Mobogenie
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: traffic school
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: sell auto notes
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: video games
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: woodpeckermp.pl
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Karl Jobst DDS
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: buy email list
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: grosir kerudung
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: andrea hair growth
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: polary
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: jual alat berat
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: My blog
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: GoPro Selfie Stick
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Read Much more
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: argent finances
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: cure impetigo
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: judi bola online
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: yuri manga
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: cerita sex dewasa
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: go here
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Related Homepag
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: cerpensex
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: escort paris
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: escort agency riga
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: girls for escorts
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: more..
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: agen judi online
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Our Webpage
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: judi bola online
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Romain Michel
    I found a great...
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: BHPH Notes
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Visit Home Page
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: abstract paintings
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: agen poker online
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: agen euro 2016
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Sell Beats Online
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: www.vx4.com
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: doball online
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: GoPro Selfie Stick
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: aviation courses
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: oil lubricant
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: oil lubricant
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: (www.bigbxl.com)
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: InfiintareSRL.com
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: buy viagra
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: server offers
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: drugs
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: drugs
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: GoPro Suction Cup
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Tooth Removing
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: 860压型设备
    广告扣板机 彩钢扣板机是专为广告行业 广告扣板机 打造的一种投资少、见效快,取材方便、广泛应用的特制设备。 彩钢扣板机 本设备所生产的产品具备外观美观、强度高,安装快捷,金辉压瓦机厂复合板机的前景预测,可多种颜色拼接安装,无明显接缝,可垂直、水平及多角度组装,间隙可调至0-6厘米,价格低廉抗风等特点。   彩钢扣板机生产出来的彩钢扣板主要适用于广告牌匾、建筑围墙装饰、室内装饰以及各种造型的封装,其超强的性价比成为装 金辉压瓦机厂复合板机的前景预测 饰材料中的佼佼者,本产品无其他材料施工后开胶脱落和表面不
  • Response
    Response: water bottle
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: colocated Servers
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Ebay Powerseller
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: roof shingles cost
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: visit link
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: i.ytimg.com
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: nude camgirl
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: agen judi online
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Ebay Shop
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Canon Cameras
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: http://Www.cuaj.ca
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Windows
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: techno website
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    I found a great...
  • Response
  • Response
    Response: fishing Area
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: ilauncher apk
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: agen bola online
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: Designer Handbags
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    Response: real facebook fans
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: المقاولون
    DiNicola Seligson
  • Response
    Response: cousin
    DiNicola Seligson
  • Response
    Response: Casino Online
    DiNicola Seligson
  • Response
    Response: Insert Your Data
    DiNicola Seligson
  • Response
    Response: buy real
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: المقاولون
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: Engine Ranking
    DiNicola Seligson & Upton - Articles (Blog) - Owner Waives Claim For Liquidated Damages By Failing To Follow Claim Procedure In AIA A201
  • Response
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: online mlm content
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: view
    DiNicola Seligson
  • Response
    Response: view
    DiNicola Seligson
  • Response
    Response: Judi online
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: bandarq
    DiNicola Seligson
  • Response
    Response: Togel 6d online
    DiNicola Seligson
  • Response
    Response: Agen qq
    DiNicola Seligson
  • Response
    Response: Sales Close
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: judi online
    DiNicola Seligson
  • Response
    Response: marketing campaign
    DiNicola Seligson
  • Response
    Response: Keep Reading
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: scr888 agent
    DiNicola Seligson
  • Response
    Response: phone sex
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: Agen poker
    DiNicola Seligson
  • Response
    Response: best online Deals
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: TV Episode
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: ex4 to mq4
    DiNicola Seligson
  • Response
    Response: these details
    DiNicola Seligson
  • Response
    Response: dizi izle
    DiNicola Seligson
  • Response
    Response: seo judi
    DiNicola Seligson
  • Response
    Response: simpsons
    DiNicola Seligson
  • Response
    Response: Www.Grauewelt.com
    DiNicola Seligson
  • Response
    Response: website
    DiNicola Seligson
  • Response
    DiNicola Seligson
  • Response
    Response: บอลสด
    DiNicola Seligson
  • Response
    Response: Bpo Services
    DiNicola Seligson

Reader Comments

There are no comments for this journal entry. To create a new comment, use the form below.

PostPost a New Comment

Enter your information below to add a new comment.

My response is on my own website »
Author Email (optional):
Author URL (optional):
Post:
 
Some HTML allowed: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <code> <em> <i> <strike> <strong>